Skip to main content
Beauchamps Close
Back

Cookies notice

By using this site you are agreeing to our cookies policy.

Close
Beauchamps
  • About us
    • About Beauchamps
    • Client service
    • Core values
    • Corporate social responsibility
    • History
    • Knowledge management
    • Partnerships
  • Our People
  • Our services

    Practice Areas

    • Banking & finance
    • Commercial property
    • Construction
    • Corporate & commercial
    • Corporate governance & company compliance
    • Crisis Management
    • Data protection & freedom of information
    • Employment & benefits
    • Energy & natural resources
    • EU, competition & procurement
    • Insolvency & corporate restructuring
    • Insurance & professional indemnity
    • Inward investment
    • Litigation & dispute resolution
    • Mergers & acquisitions
    • Personal injury*
    • Planning & environmental
    • Private client & family law

    Sectors

    • Brexit
    • Charities & not for profit
    • Energy & natural resources
    • Family business
    • Financial services
    • Food & agri
    • Healthcare
    • Housing
    • Real estate
    • Retail
    • Sport
    • Technology & communications
    View All Services
  • What's new
    • Beauchamps - proud sponsor of and official legal adviser to Leinster Rugby
    • Brexit Update
    • Doing business in Ireland
    • General Data Protection Regulation
    • The Companies Act 2014
  • Join us
    • Why join Beauchamps?
    • Current opportunities
    • Legal professionals
    • Business support
    • Intern & trainee programmes
Contact Search
Search Menu
Beauchamps
Search Menu
What's new

Fitness for purpose obligations – what contractors and developers should know

08 Oct 2018

Breadcrumb

  1. Home
  2. What's new
  3. Publication

Share

The August 2017 UK Supreme Court decision in MT Højgaard A/S  (MTH) v E.ON Climate and Renewables UK Robin Rigg East Limited & Anor provides key lessons for interpreting fit for purpose obligations in construction contracts.

While this case is not binding in Ireland, it is persuasive authority for the Irish courts. It involved a design failure in the steel foundation structures of a 60 turbine offshore wind farm in Solway Firth. MTH as the contractor completed those works in February 2009 and within 14 months they started to fail.

Main dispute

The main dispute was over who was liable for the €26 million cost of rectification works. MTH complied with the contractual requirement to design in accordance with the international design standard J101, which was supposed to ensure a service life of 20 years for the steel structures. However later in 2009 a significant error in J101 was discovered which meant structures designed in accordance with it were likely to have a much shorter service life than 20 years. There was also a fit for purpose obligation in the contract and the Technical Requirements required that the foundations be designed to “ensure a lifetime of 20 years in every respect without planned replacement”.

Court decision

The Court held that complying with J101 was a minimum requirement and the contract obliged MTH to identify areas where a more rigorous design was required. The Court noted that each contractual provision had to be given effect, so the fit for purpose obligation also applied which was not inconsistent with MTH having to comply with J101. It was also held that MTH failed to identify the need to improve on J101 and failed to meet the fit for purpose obligation.

Learning Points

There were a number of lessons to be learned from this case:

  • Contractors should be aware of fit for purpose obligations requiring the achievement of a particular result, which is a higher standard than exercising reasonable skill and care. A fit for purpose obligation can be expressly stated, however one may still arise where a contractor warrants that the works will comply with the performance specification or the employer’s requirements.
  • This case shows the importance of good communication between a client’s technical and legal advisers to ensure that design and construction standards in different parts of a contract are consistent.
  • There was no priorities clause in the contract to specify which document prevails where they conflicted. However the Court considered that such a clause would not have affected its decision as the different parts of the contract did not conflict.
  • While a client may want a fit for purpose obligation to transfer the risk to a contractor to achieve a desired result, contractors will generally price for this. Fit for purpose obligations in respect of design are often uninsurable in Ireland.
  • The lessons in this case also apply to the pricing and insurance obligations in a contract which should be cross checked against the relevant schedules to ensure they are consistent.

MT Højgaard A/S  v E.ON Climate and Renewables UK Robin Rigg East Limited & Anor [2017] UKSC59 

About the author

David Gunn

Partner

About David

David is a partner in our energy & natural resources team. He has over 10 years’ experience advising developers, funders and the public sector in the energy industry including wind projects, solar, hydro, biomass, anaerobic digestion and power plant operators. He also advises clients on the financing and construction of commercial and industrial developments, housing, materials recovery facilities, water treatment plants, educational campuses and infrastructure.

Beauchamps

Related Services

Practice Areas

    Energy & natural resources

Sectors

    Energy & natural resources
Beauchamps

Our Location

Riverside Two

Sir John Rogerson's Quay

Dublin 2, D02 KV60

Ireland, DX No. 63

General Enquiries

T: +353 (0) 1 418 0600

F: + 353 (0) 1 418 0699

E: info@beauchamps.ie

  • Cookie Policy
  • Disclaimer
  • Accessibility
  • Sitemap
  • Contact
  • Privacy
Website by Strata3